QUESTION 119
Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?

 
 
 
 

QUESTION 120
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

 
 
 
 

QUESTION 121
You are the project manager for BlueWell Inc. Your current project is a high priority and high profile project within your organization. You want to identify the project stakeholders that will have the most power in relation to their interest on your project. This will help you plan for project risks, stakeholder management, and ongoing communication with the key stakeholders in your project. In this process of stakeholder analysis, what type of a grid or model should you create based on
these conditions?

 
 
 
 

QUESTION 122
You are the project manager of the NJJ project. Your enterprise environmental factors require that you establish certain risk management rules regarding low risks within your project. What is the best policy for risks with low probability and low impact in the project management?

 
 
 
 

QUESTION 123
Which risk response is acceptable for both positive and negative risk events?

 
 
 
 

QUESTION 124
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that you assess the probability and what other characteristic of each identified risk in the project?

 
 
 
 

QUESTION 125
You are the project manager of the NHQ Project for your company. You have completed qualitative and quantitative analysis of your identified project risks and you would now like to find an approach to increase project opportunities and to reduce threats within the project. What project management process would best help you?

 
 
 
 

QUESTION 126
Which of the following represents the best description of the role of project manager for project risk management?

 
 
 
 

QUESTION 127
You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

 
 
 
 

QUESTION 128
Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on the project. Bill discusses the risk event with Virginia, the primary project customer, and she decides that the requirements surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high risk exposure. What risk response has been enacted in this project?

 
 
 
 

QUESTION 129
Don is the project manager of the PFO project for his organization. Don is working with the project team members and two subject matter experts to assess the identified risk events in the project. Which of the following approaches is the best to assess the risk events in the project?

 
 
 
 

QUESTION 130
Two companies merge. The executive leadership team for the newly formed company hires a project risk manager to integrate both companies’ technology platforms into a single global platform. Since success of this integration project is critical for the new company, the project risk manager determines that risk management is vital.
What factors does risk response planning include?

 
 
 
 

QUESTION 131
Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?

 
 
 
 

QUESTION 132
You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you create to accomplish the task?

 
 
 
 

QUESTION 133
Which of the following techniques for planning risk response can provide a means of identifying symptoms for use as trigger conditions for contingency responses?

 
 
 
 

QUESTION 134
Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the following statements is the most accurate about when project risk happens?

 
 
 
 

QUESTION 135
Ben works as a project manager for the MJH Project. In this project, Ben is preparing to identify stakeholders so he can communicate project requirements, status, and risks. Ben has elected to use a salience model as part of his stakeholder identification process. Which of the following activities best describes a salience model?

 
 
 
 

QUESTION 136
A project team’s risk facilitator identifies a number of risks and must prioritize them based on the organization’s risk appetite levels. Which technique should be used?

 
 
 
 

QUESTION 137
Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?

 
 
 
 

QUESTION 138
During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites. The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process.
What should the project manager do next?

 
 
 
 

QUESTION 139
Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?

 
 
 
 

QUESTION 140
You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated. Which type of strategies have you used to deal with the risks involved with that particular work?

 
 
 
 

Exam Info

The candidates will have 210 minutes to answer 170 questions presented in the multiple-choice format. Please note that there are 20 unscored items, which will be placed throughout the subject areas as the pretest questions. This exam can be taken in the English language, and the students must pay the fee of $520 (for PMI members) or $670 (for non-members) to schedule the test. As for the registration process, it can be done through the Pearson VUE platform.

 

Earn Quick And Easy Success With PMI-RMP Dumps: https://www.testsimulate.com/PMI-RMP-study-materials.html

Related Links: myportal.utt.edu.tt www.stes.tyc.edu.tw www.stes.tyc.edu.tw myportal.utt.edu.tt youemerge.com www.stes.tyc.edu.tw

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below